Abstract:
In Ethiopian, under a government regulatory body, i.e. South Roads Authority, number of
road construction projects is increasing from time to time. However, it becomes difficult to
complete projects in the allocated budget. Cost overrun is one of the major problems of road
construction projects undertook by South Roads Authority. This project was carried out to
assess and rank the severity of major factors that cause cost overrun during construction
projects in the Corporation. Questionnaire surveys together with desk study were used to
collect data on time and cost overrun. The south roads authority have a total of above 1000
workers in all 12 district and head office level in addition to over 100 workers from south
nation nationality people representatives transport bureau I have selected only 75
respondents which means 23 from client, 27 from contractor and 25 from consultant by using
stratified random sampling technique. A total of 67 valid responses comprising 21 clients,
26 contractors and 20 consultants were collected and a desk study of 6 completed road
construction projects in South Roads Authority Hossana district were investigated. The data
was subjected to descriptive statistical analysis and subsequently mean scores were
determined to rank factors level of severity. From the study it was found that all of road
construction projects finished with severe cost overrun. The rate of cost overrun ranges from
minimum of 8.26% to the maximum of 23.55% for individual projects of the work executed
and certified amount. The study identified 20 causes of cost overrun for the case of South
Roads Authority. The most important causes of cost overrun were found to be Inflation of
construction material price with weighted average mean score of 3.97, Delay in release of
budget allocated for the project with weighted average mean score of 3.88, Increasing the
price of fuel with weighted average mean score of 3.72, Types of contract used in the
organization and Fluctuation of foreign currency exchange rate with weighted average mean
score of 3.67 and Unavailability of quarry (gravel material) on the site or near the site with
weighted average mean score of 3.67 are the six most important factors affecting cost of
construction projects. It is likely that these findings will help focus on very significant factors
to improve the construction performance of the Authority in the future